U.S. Route 30 and State Route 43 signs in Canton, OhioU.S. Route 30 in Canton. Photo: TheCatalyst31, CC BY-SA

CANTON, Ohio — The long push to relocate U.S. Route 30 east of Canton has picked up another $3 million in proposed state support, as Ohio’s Transportation Review Advisory Council included the project in its draft major new construction program for fiscal years 2027 through 2030. The money, proposed for fiscal year 2028, would pay for right-of-way acquisition and environmental mitigation on the Stark County project, according to the Ohio Department of Transportation.

Stark County Commissioner Richard Regula, a longtime proponent of the relocation, welcomed the proposal in comments reported by The Repository. “That’s $3 million, and we can use it for right-of-way and environmental,” Regula told The Repository. “We’re excited, we’re appreciative, and we’re getting a lot of traction.” Regula also told The Repository that the funding “keeps it moving forward,” and he called it another step in the right direction for a project local officials have pursued for years.

Advertise your business here

The U.S. 30 relocation would build a new 3.6-mile highway connection from Trump Avenue to State Route 44, east of Canton, according to The Repository’s reporting. The Ohio Department of Transportation has already begun acquiring right-of-way for that first section, but several parcels remain, Regula told The Repository. The proposed $3 million is aimed squarely at that unfinished work — buying the land the highway will need and completing the environmental mitigation that must accompany a new road built across previously undeveloped ground.

The Stark County award is one piece of a much larger statewide list. The Transportation Review Advisory Council, known as TRAC, tentatively approved a draft funding list totaling $46.7 million for 13 projects in 12 counties, the Ohio Department of Transportation said in its announcement of the draft list. Of that total, $37.1 million covers 12 projects, and TRAC allocated an additional $9.6 million in fiscal year 2028 to fully fund construction of the Interstate 275 SmartLane project in Clermont and Hamilton counties, according to the department.

TRAC was established in Ohio law in 1997 to help the Ohio Department of Transportation select projects for the state’s Major New Capacity Program, according to the department. Inclusion on the draft list is a significant milestone for a local project, but it is not the final word — the list still has to survive a public comment period and a final vote.

For Stark County, the stakes in that process extend well beyond the first 3.6 miles. Officials are also working toward a long-term goal of extending the U.S. 30 expressway southeast of Route 44 by more than 30 miles, past Minerva and through Columbiana County to State Route 11, with future work in the area possibly including a connector highway south to Carrollton, according to The Repository. The eventual goal, The Repository reported, is to connect Stark County directly with the greater Pittsburgh area and with the Shell Pennsylvania Petrochemical Complex in western Pennsylvania.

Regula framed that larger vision in economic and safety terms in his comments to The Repository. “We need to build a good, safe, four-lane highway from not only from Trump to 44, but 44 clear to Route 11,” he told The Repository. “That ties into the energy corridor. … It really can put Ohio, especially Northeast Ohio, on the map for decades to come.” Altogether, The Repository reported, the project aims to improve safety for motorists and encourage economic development, and Regula said officials are concentrating first on securing funds for the Trump Avenue to Route 44 section because investment in that initial portion could attract more interest in the overall project.

The corridor is one of several Northeast Ohio road stories this month. In Summit County, drivers recently regained a long-closed crossing when Munroe Falls reopened the Route 91 bridge after a closure that began in June. Road agencies are also bracing for winter costs, as six Northeast Ohio counties asked Governor Mike DeWine for help after a flooded salt mine cut into their winter supply.

What we know — and what we’re still waiting on

What is confirmed: TRAC has tentatively approved the $3 million for the U.S. 30 relocation in its draft fiscal years 2027-2030 list, the money would be awarded in fiscal year 2028, and it is designated for right-of-way and environmental mitigation, according to the Ohio Department of Transportation and The Repository. What is not yet final: the funding itself. The draft list remains a proposal until TRAC votes on the final version, and no construction timetable for the relocated highway has been announced in connection with this funding round.

Advertise your business here

Residents who want a say in that decision still have time. The public comment period for the draft funding plan is open until December 9, 2026, and comments can be sent to [email protected], according to the Ohio Department of Transportation. TRAC will then vote on the final list at its December 17, 2026 meeting — the concrete next step that will determine whether the $3 million for Stark County moves from a draft line item to a firm state commitment.

Regula, for his part, made clear to The Repository that local advocates do not intend to let the project stall while that process plays out. Next steps include continuing the push for public and private investment, he told The Repository. “I’m in for the long haul on this one,” he told The Repository — a stance Stark County drivers who use the existing U.S. 30 corridor every day will be watching as the December 17, 2026 vote approaches.

Photo: TheCatalyst31, CC BY-SA

By Dan Whitmore