MUNROE FALLS, Ohio — Drivers in Munroe Falls are crossing the Cuyahoga River on State Route 91 again, after the replacement bridge and the adjoining railroad area reopened to vehicle traffic, the Akron Beacon Journal reported.
The city posted on social media on the afternoon of Monday, November 23, 2026, that the area was open, ending a closure that began in June and frustrated residents and business owners across the area, the Beacon Journal reported. The bridge stands near Brust Park.
The $2.1 million project was led by the Ohio Department of Transportation, which replaced the bridge’s concrete driving surface, made structural repairs, installed new guardrails on both sides of the road and replaced the sidewalk, according to ODOT information reported by the Beacon Journal. New supports were also installed for the sanitary sewer on the bridge’s east side and a gas line on its west side.
The state’s own work finished earlier in the fall, but the road could not reopen until two other jobs on the same stretch were done: CSX’s replacement of the railroad crossing just south of the bridge, and the city’s waterline repairs, the Beacon Journal reported.
“ODOT’s work is completed. Once the railroad and city are completed with their projects, it will be opened up,” Justin Chesnic of the Ohio Department of Transportation told the Akron Beacon Journal while the crossing work continued. Munroe Falls public service director James Bowrey said the CSX crossing replacement was the final piece preventing the opening, the Beacon Journal reported.
What we know — and what we’re still waiting on
What is confirmed: Route 91 between North River Road and Munroe Falls Avenue carried traffic again as of November 23, 2026, after a closure that stretched from June through a series of revised opening dates — first August, then mid-October, then November 10, according to the Beacon Journal’s reporting. What remains open: a sanitary line installation expected in the coming weeks and bridge painting that has been pushed to spring 2027, the Beacon Journal reported.
The closure’s length was the story for much of the fall. ODOT cited difficulty obtaining a key component — elastomeric bearings — among the supply problems that stretched a project first expected to take about 45 days into a roughly five-month closure, the Beacon Journal reported.
For businesses along the corridor, the reopening restores the direct route through the city just before the Thanksgiving travel period, and access to Brust Park, which stayed open throughout construction, is back to normal.
What happens next: drivers should still expect occasional finishing work around the corridor in the coming weeks, including the sanitary line installation, while the painting waits for spring 2027 weather, according to the Beacon Journal.