Power Siting Board OKs Two Gas Plants to Feed Data Centers in Fairfield, PickawayThe Guernsey Power Station in Guernsey County, an Ohio natural gas-fired plant of the kind approved for Fairfield and Pickaway counties on November 19, 2026. Photo: TomStonehunter, CC BY-SA 4.0

The Ohio Power Siting Board has approved two natural gas-fired power plants that will generate electricity exclusively for nearby data centers, clearing the way for construction in Fairfield County and Pickaway County and reaffirming a contested solar project in Madison County in the same November 19, 2026 meeting.

According to the board’s media release, reported by The Columbus Dispatch, Fairfield Energy Center LLC won approval to build and operate a 1,350-megawatt generation facility and a 1,040-megawatt battery energy storage facility on 122 acres near State Route 37 and State Route 204 in the Village of Millersport, southwest of Buckeye Lake. The plant will serve the Vantage Data Center OH2 campus, a development of up to four data centers being built on more than 350 acres annexed from Walnut Township into Millersport.

PowerConneX Inc. received approval at the same meeting to construct and operate the 800-megawatt Asheville Energy Center on 110 acres along State Route 752, east of State Route 23, in Pickaway County. Both facilities are what regulators call behind-the-meter generation: the power they produce flows directly to the adjacent data centers rather than onto the regional electric grid.

The approvals come with long lists of conditions. The Fairfield project must meet 36 conditions, including obtaining all construction permits, developing emergency response and safety plans before construction begins, notifying the Ohio Environmental Protection Agency of any environmental impacts from construction, and restricting herbicide use near surface waters. The Asheville project carries 41 conditions, among them commitments to contribute millions of dollars toward local parks, recreation and capital improvement projects, limits on most construction activity to between 7:00 AM and 7:00 PM, and an environmental specialist on site during construction in sensitive areas, according to the stipulations reported by The Columbus Dispatch.

The decisions land in the middle of Ohio’s fast-moving debate over how the data center boom should be powered and who should pay for it. Central Ohio has become one of the nation’s largest data center markets, and state regulators have spent the past two years wrestling with grid capacity, ratepayer costs and the tax incentives that draw the projects. A Franklin County study released this month questioned whether the property tax breaks used to attract development pay back their cost for decades — a question that now sits alongside the power question in Millersport and Asheville. Readers can follow that side of the debate in our coverage of the Franklin County tax incentive study.

In a separate action at the same meeting, the board reaffirmed its approval of the Oak Run Solar Project in Madison County, an 800-megawatt solar facility with two transmission lines and 300 megawatts of storage across roughly 4,400 acres in Monroe, Somerford and Deercreek townships. The Ohio Supreme Court had sent the case back to the board over whether the project had provided adequate visual simulations of its substation components; the board stood by its September 2026 finding that the facility would have a minimal overall aesthetic impact and reissued its certificate of environmental compatibility, The Columbus Dispatch reported.

What we know — and what we’re still waiting on

What is confirmed: both gas plants and their battery storage components are approved, the conditions attached to each approval are public, and neither plant will connect its output to the general grid. What remains open: construction start dates for both facilities, the construction timelines for the data center campuses they will serve, and whether opponents of any of the three projects pursue further appeals. The siting board has jurisdiction over the generation facilities themselves, but not over approval of the data centers they power — those decisions rest with local governments.

For residents near Millersport and Asheville, the practical effects arrive in stages: construction traffic and jobs first, then permanent operations at sites that will rank among the largest power facilities in their counties. The local benefit commitments attached to the Asheville approval — the parks and capital improvement funding — will be tracked by Pickaway County officials as construction proceeds.

What happens next: both developers must satisfy their pre-construction conditions, including permits and emergency plans, before work begins, and the Oak Run decision can still be tested in court by the project’s opponents. NewsForce247 will follow the construction filings and the first local hearings as the projects move from paper to ground.

Photo: TomStonehunter, CC BY-SA 4.0

By Grant Ellison

Grant Ellison covers Ohio business and agriculture — Main Street storefronts, manufacturers, grain markets, and the farm economy that feeds the state.