WAVERLY, Ohio — Pike County residents packed the conference room at the Pike County Government Center on Tuesday night, November 24, 2026, and talked for more than three and a half hours about the data center campus proposed for the former Portsmouth Gaseous Diffusion Plant site near Piketon, according to J News Network, which reviewed a full recording of the meeting and checked every quote in its account against that recording.
The special meeting of the Board of County Commissioners was a public comment session on the term sheet for the PORTS-Pike Technology Campus, the project SB Energy proposes to build at and around the former plant, J News Network reported. The board approved the non-binding term sheet on November 18, 2026, by Resolution No. 1011-26, and said it expected no formal action on Tuesday night, with speakers held to three minutes each.
John Oberle, a partner with Ice Miller LLP, the firm representing Pike County on the project, opened the county’s presentation by telling the room where things stand. “Nothing has been decided,” he told the meeting, according to J News Network. “We want comments, we want openness.” Negotiations with the company began in July, he said, no final agreement has been signed, and the term sheet binds no one.
The scale Oberle described is enormous by any Ohio standard: power plants with “10 gigawatts of power,” “up to 17 data centers,” and “25 to 30,000 construction workers in this community,” according to J News Network’s account of his presentation. “It’s going to be some disruption,” he said. “There’s going to be short-term pain for long-term gain in Pike County.”
The money, as Oberle presented it to the room, includes up to $300 million in upfront dollars negotiated from the company — “I think this package is going to be the biggest package in Ohio’s history,” he said, according to J News Network — and, in exchange for a 100 percent tax abatement on the buildings, up to $1.5 billion in payments in lieu of taxes, with $120 million of it arriving within three years, before construction is even complete. He also cited a guaranteed minimum of $150 million a year in sales tax and up to $6 million from the company to cover the county’s own legal and engineering costs.
Residents answered with the site’s history. Vina Colley, president of Portsmouth Piketon Residents for Environmental Safety and Security and a former plant electrician, filed detailed technical and legal written comments with the board and told commissioners the term sheet is not a final contract — meaning, in her argument as reported by J News Network, that the board still has the power to protect residents before signing anything binding. Speakers through the evening raised land contamination, family illness, water, noise, and homes, according to J News Network.
What we know — and what we’re still waiting on: the term sheet is approved but non-binding, no final agreement has been signed, and Tuesday’s meeting took no formal action — all confirmed in J News Network’s account. What is not yet public is any final agreement’s terms: the binding commitments on testing, water, and payments will only be known when a contract is presented.
The Pike County site is unlike almost any other data center site in the state: a former uranium enrichment plant with a documented contamination legacy, in one of Ohio’s poorest counties, now proposed for one of the largest technology campuses in the country. That combination is why a routine term-sheet comment session drew a packed room and three and a half hours of testimony.
What happens next: negotiations between the county and the company continue, and any final agreement must come back before the Board of County Commissioners. Until a binding contract is signed, Tuesday night’s message from the room in Waverly stands — the county’s own lawyer says nothing has been decided, and residents intend to keep showing up while that is true.