COLUMBUS, Ohio — Ohio State University’s new combined heat and power plant is operating on west campus, three years after its original completion date, with the total project cost expected to exceed $585 million — more than double the original $278 million estimate, The Lantern reported.
The plant began operating in early September 2026, according to The Lantern. University spokesperson Dan Hedman said in an email that Ohio State’s financial responsibility for the project is $349 million, while the overall project cost is expected to exceed $585 million, The Lantern reported.
The final project cost is still being calculated by ENGIE Buckeye Operations, according to Hedman, as quoted by The Lantern. The Columbus Dispatch reported that the 105-megawatt natural gas plant will power a significant portion of campus, including the Innovation District, and that any costs beyond $349 million are the responsibility of Engie to pay.
The plant was initially estimated to cost $278 million when the Ohio Power Siting Board approved its construction in September 2020, The Lantern reported, and the estimate was later revised to $289.9 million before the total climbed past $585 million.
“The actual savings will be easier to quantify once we have more of an operating history, given the plant has only been operational since early September,” Hedman said, as quoted by The Lantern — a direct quote from Ohio State’s spokesperson carried in The Lantern’s reporting.
What happens next: ENGIE Buckeye Operations finishes calculating the final total, and Ohio State measures the plant’s actual savings against its projections now that the facility is running. The plant’s opening closes one of the university’s longest and most expensive construction sagas — approved in 2020 at $278 million, delivered in 2026 at more than twice that figure.