LANCASTER, Ohio — Lancaster City Council voted 10-0 on Monday, November 23, 2026, to limit how close data centers can be built to the city’s homes, passing an ordinance that requires a 500-foot setback between a data center and nearby residents, the Lancaster Eagle-Gazette reported.
The vote followed a public hearing at which about 100 people attended and roughly 20 addressed council, with most speakers supporting the move to restrict how far a data center can approach a neighboring property, according to the Lancaster Eagle-Gazette. The ordinance also requires a data center’s power generating station to sit 650 feet away from nearby residents.
Council did not go as far as first proposed. The original ordinance called for a 1,000-foot setback, but council amended it to the shorter distances before passing it, the Lancaster Eagle-Gazette reported. The city’s planning commission had recommended the 1,000-foot figure, a point NBC4’s reporting on the hearing also noted, meaning the final ordinance splits that recommendation in half.
The new mandate applies to any new data centers that may open in Lancaster and to any expansion at Google’s current data center in the Whiley Road area, according to the Lancaster Eagle-Gazette. NBC4 reported that Google is expanding its data center footprint in Fairfield County and recently bought more land, the growth that pushed the setback question in front of council.
Under the city’s old rules, the protection was far thinner. The previous code tied the setback to building height — about a foot of distance for every foot of height — so a 60-foot data center could be built roughly 60 feet from a home, as residents pointed out in the public campaign for the new section of city code.
Nearby residents have complained of noise, a diesel fuel smell and bright lights coming from the existing data center, the Lancaster Eagle-Gazette reported. Those complaints, repeated across months of meetings, were the backdrop for Monday night’s hearing and for the crowd that turned out for it.
Not everyone left satisfied. Dan and Meg Fruth, who live on Wilson Road near the Google data center, told the Lancaster Eagle-Gazette the amended setbacks fall short. “But it’s not nearly enough,” Meg Fruth told the Eagle-Gazette, and her husband agreed the setbacks are not far enough back. Dan Fruth told the Eagle-Gazette he believed the hearing itself was, in his words, choreographed and staged.
Other speakers weighed Google’s presence differently. Council member Connell noted, as the Lancaster Eagle-Gazette reported, that if not for Google and two other donors there would not have been a 2026 Lancaster Festival following last year’s devastating floods that wiped out most of the festival — a reminder that the company is also one of the city’s significant civic benefactors.
Lancaster is not deciding this question alone in Ohio. Communities across the state are writing their first data center rules as the facilities multiply, including Chillicothe, where residents helped write the city’s first rules for data centers, and Findlay, where council ended its year with no votes on data center zoning. Lancaster’s ordinance now gives this city a settled rule where many Ohio communities still have none.
What we know — and what we’re still waiting on: What is confirmed is the 10-0 vote, the 500-foot setback for data centers and the 650-foot setback for their power generating stations, and that the rule covers both new facilities and expansion at Google’s Whiley Road site. What is not yet known is whether Google will adjust its Fairfield County expansion plans under the new distances, and whether residents who pushed for 1,000 feet will ask council to revisit the ordinance.
What happens next is implementation: any new data center proposal, and any expansion at the Whiley Road site, will be measured against the 500-foot and 650-foot lines council drew on Monday night. For the neighbors who filled the hearing room, the ordinance is the first enforceable distance the city has ever put between their homes and the industry’s buildings.