Chillicothe drivers are in the thick of the roughest two days of the Bridge Street rebuild this week, with restriping work cutting the city’s busiest commercial corridor to one lane in each direction on Tuesday and Wednesday before all lanes are set to reopen in their final winter configuration on Thursday morning.
The Ohio Department of Transportation announced the schedule on Friday, and it is running a week early, according to the Scioto Valley Guardian’s report of ODOT’s announcement. Southbound lanes through the U.S. 35 interchange had been closed since late March.
“Some major changes are coming as we get both directions of Bridge Street re-opened, as promised, ahead of Thanksgiving,” ODOT press secretary Matt Bruning told the Scioto Valley Guardian. Traffic began moving in both directions again by Monday evening, November 16, after crews spent Sunday and Monday prepping and painting lane markings on the new northbound lanes between Riverside Drive and Marietta Road.
The timing is driven by the weather, not the calendar. “Because temperatures must be warmer for the paint to properly be applied and dry, the work must be done during the day and cannot be completed at night,” Bruning told the Scioto Valley Guardian — which is why the lane restrictions land in the middle of daytime traffic on the corridor that links downtown Chillicothe, the U.S. 35 interchange, the city’s big-box stores and the Chillicothe Mall.
On Tuesday and Wednesday, November 17 and 18, crews restripe the stretch from Marietta Road to the Chillicothe Mall and Zane Plaza, and ODOT said major delays are again anticipated, the Guardian reported. Bruning also reminded motorists not to enter signalized intersections until they can clear them. “Blocking intersections will cause additional delays along this busy corridor,” he told the Scioto Valley Guardian.
Drivers will also find a new pattern at Bridge Street and Stewart Road. New traffic signals have not yet been installed there, so the intersection will not function at an optimal level, Bruning told the Guardian, but the final traffic pattern takes effect once all lanes reopen: both northbound and southbound traffic may turn left from Bridge Street, while all traffic leaving the Shawnee Square shopping center and Stewart Road must turn right.
What we know — and what we’re still waiting on
What is confirmed, from ODOT through the Scioto Valley Guardian: both directions reopened Monday evening; one lane each way on Tuesday and Wednesday for restriping; and a goal of three lanes in each direction in final winter configuration by Thursday morning, November 19. What is not yet settled: whether weather holds for the painting schedule — ODOT says all work is weather dependent — and how the unfinished Stewart Road signals will affect the corridor’s first days in the new pattern.
The reopening is a milestone in the State Route 159 Bridge Street Safety Improvements project, a $19.29 million rebuild that began in spring 2025 and is scheduled to end in summer 2027, according to ODOT. The plan adds a northbound lane from Stewart Road to north of Pawnee Road, creates a southbound drop lane to the westbound U.S. 35 ramp, realigns the interchange ramps on new concrete, and adds a shared-use path, sidewalks, new signals at seven intersections, a new access road called Marietta Road and a roundabout on River Trace near Walmart. ODOT identified several intersections along the corridor with high crash rates between 2014 and 2018, particularly rear-end collisions driven by congestion.
The work is not finished when the lanes reopen. Additional lane closures are coming on the southbound side after Thanksgiving so crews can remove the temporary on-ramp to westbound U.S. 35 and install curb, gutter and guardrail, ODOT said. That work is expected to begin Monday, November 30, and take three days, with intermittent daytime lane closures possible through mid-December — but no additional full closures planned. Major construction then pauses for the winter, resuming in the spring of 2027 with work ODOT says will be much less disruptive.
For Southeast Ohio readers following the region this week, NewsForce247 has also covered the E. coli investigation at Ohio University in Athens and the Athens County Sheriff’s sober-ride push ahead of Thanksgiving travel.
What happens next: if the painting stays on schedule, Thursday morning brings the first full-width commute on Bridge Street since March. ODOT posts traffic impacts for the project at transportation.ohio.gov/bridgestreet, and questions can go to the ODOT District 9 public information office at 740-774-8834.