ATHENS, Ohio — The Athens County Board of Commissioners has agreed to award the contract to clear the logjam beneath the Currier Street bike path bridge to McKee Auto Parts of New Marshfield, The Athens Messenger reported.

McKee Auto Parts’ bid of $96,000 was the lowest of the six bids received by the Athens County Planning Commission Office, The Athens Messenger reported. The remaining bids ranged from $109,000 to $340,000.

Advertise your business here

The contract requires the contractor to remove the logs in a way that would not allow them to drift downstream, along with separating and recycling any solid waste present in the logjam, The Athens Messenger reported.

The city of Athens and the county will split the cost of the removal, though the split depends on whether the county can use approximately $78,000 it received from the Ohio Attorney General’s Office, Athens County Planner Connor LaVelle explained, according to The Athens Messenger. That money had been earmarked for cleaning up an illegal dumpsite at Cherry Ridge Road in Alexander Township.

Advertise your business here

The dumpsite money would only cover part of that site’s remediation, with the full cost estimated at around $120,000, so the county wants to find out whether the attorney general’s office will allow it to use the funding on the river logjam instead, The Athens Messenger reported. The shift would tie into the funding’s original purpose: detritus such as bottles, cans, styrofoam and even refrigerators can be seen stuck in the logjam, Commissioner Chris Chmiel explained, according to The Athens Messenger.

If the attorney general’s money cannot be used, the city has offered to pay half of the project cost, though doing so would require action by Athens City Council; if the money is made available, the city will contribute only $9,000, LaVelle explained, according to The Athens Messenger. What happens next is the funding decision, and then the clearing work under the bike path bridge.

Photo: Tim Kiser, CC BY-SA

By Marcus Webb

Marcus Webb is an overnight reporter for NewsForce247, covering breaking news and developing stories across Ohio through the night — public safety, weather, and the overnight wire.

Leave a Reply

Your email address will not be published. Required fields are marked *