AKRON, Ohio — Akron Public Schools will build an entirely new North High School instead of preserving part of the current building, after the school board voted 5-2 on Monday, November 23, 2026 to redesign the $85 million replacement project as construction costs rose, the Akron Beacon Journal reported.
North High School, at 985 Gorge Boulevard, serves roughly 900 students in a nearly 266,000-square-foot building, the Akron Beacon Journal reported. It is the district’s only neighborhood high school that was not replaced during the 15-year effort by the district and the city that produced more than 30 new community learning centers across Akron.
The new school will serve North Hill’s growing immigrant population and is being designed for 1,100 students in grades 9 through 12 and 150 employees, according to the Akron Beacon Journal. Voters approved the $85 million bond issue that funds the project in November 2024, and board members have been adamant the project must stay within that $85 million, the Beacon Journal reported.
Under the planning parameters the board approved, the replacement will be an all-new building of roughly 168,000 square feet — more than 97,000 square feet smaller than the existing school — built on the site of the school’s existing practice field, the Akron Beacon Journal reported. Signal Akron reported the plan also includes a grass practice field, an asphalt track, a 750-seat auditorium, a competition gym and an auxiliary gym, while dedicated space for preschool, robotics and career programs has not yet been settled.
The vote replaces the design the board approved in February, which would have preserved part of the existing building. Rising construction costs forced the change, the Akron Beacon Journal reported, and the board has not discussed seeking additional funding beyond the voter-approved bond.
Board members Nathan Jarosz and Summer Hall voted against the new design, the Akron Beacon Journal reported. Signal Akron reported Jarosz acknowledged the difficult balance between the needs of North Hill’s growing community and the project’s strict budget.
The project has been years in the making. Akron Public Schools’ project page records the board’s February 23, 2026 approval and a first community meeting on October 9, 2025, and the district describes the new building and athletic fields rising on the current site while the current North High stays open throughout construction. Monday’s vote was the moment the February direction — part preservation, part new construction — gave way to a single all-new building.
North is Akron’s growth story at a moment when much of the district is not growing: Signal Akron has reported the North cluster is the only part of the district projecting enrollment growth, driven by North Hill’s immigrant community, and its preschool and career programs — including an early-childhood education pathway Signal Akron described as one of a kind in Ohio — are among the spaces whose future footprint is still being debated. It is a big week for Akron education and athletics alike, from the classroom vote to a Hudson runner’s Olympic Marathon Trials qualification and the end of the Akron Zips football season.
What we know — and what we’re still waiting on: The board’s 5-2 vote, the $85 million cap, the 168,000-square-foot all-new design and the 1,100-student capacity are confirmed by the Akron Beacon Journal and Signal Akron. Still unsettled are the dedicated spaces for preschool, robotics and career programs, and whether the new building can still open in the fall of 2029.
The timeline is the open question. The board’s November 23 approval lets architects refine the design and produce the detailed drawings and specifications used to seek contractor price proposals, the Akron Beacon Journal reported, but members of the design team have indicated the project may not be completed in the fall of 2029 as originally planned. Akron Public Schools’ project page lists construction running from the spring of 2027 into the winter of 2029-30, with the current building remaining in operation while the new one rises on the same site.
For North Hill families, the decision settles the biggest question — a wholly new school, on the same grounds, at the price voters approved — while leaving the program-by-program details to the design work ahead.
What happens next: the design team refines the all-new plan and produces detailed drawings for contractor pricing, and the district settles the remaining program spaces, including preschool, robotics and career pathways, within the $85 million budget.