Lucas County commissioners voted on Tuesday, November 17, 2026 to open negotiations with two Toledo firms to plan a renovation of the Lucas County Corrections Center in downtown Toledo, a project that could cost as much as $77 million, WTVG 13abc reported.

The commissioners authorized negotiations with SSOE Group for architectural and engineering services and with Mosser Construction for construction management work ahead of building, according to WTVG. The jail, on Spielbusch Avenue in downtown Toledo, would be renovated rather than replaced, and construction has not begun.

The vote ends — at least for now — a long county argument about what to do with its jail. Lucas County spent years pursuing a new pretrial detention center: in May 2023 the commissioners announced a three-acre downtown site at Canton and Southard streets for a roughly 217,000-square-foot facility designed to house 430 people, with completion then planned for the fall of 2026, according to a Lucas County release at the time. That replacement plan was later abandoned, and the county pivoted to renovating the existing corrections center after years of failed efforts, the Fostoria Free Press reported.

Sheriff Mike Navarre, whose office runs the jail day to day, welcomed the decision to move forward and to hire a local firm, WTVG reported. But the sheriff and the commissioners are split over one design question that will shape the whole project: whether the renovated jail’s housing units should be built for direct supervision, a model in which officers are stationed inside the housing units with the people held there.

Navarre wants SSOE free to price a direct-supervision layout as part of its design work, and he warned that if the commissioners refuse to let the firm determine the cost of direct-supervision housing units, he intends to hire another company to perform that initial study using funds the commissioners do not control, WTVG reported.

The design model at issue changes how a jail is staffed, not just how it is built. Under direct supervision, corrections officers work inside the housing unit alongside the people held there, rather than watching from a control room or on intermittent rounds — a layout that requires the units themselves to be designed around an officer’s post, sight lines and smaller groupings of cells or dormitory beds. Retrofitting that model into an existing building is a different, and usually more complicated, design problem than building it new, which is why the sheriff wants the option priced before the renovation’s scope is locked rather than after.

Advertise your business here

The money question runs alongside the design question. The renovation’s cost has been estimated at up to $77 million to improve living conditions and safety for staff and for the people held at the jail, according to WTVG, and the county has spent years assembling state and local funding for a jail project whose form kept changing.

What we know — and what we’re still waiting on: What is confirmed is the November 17, 2026 vote itself — negotiations are authorized with SSOE Group and Mosser Construction, no construction contract exists yet, and no final price has been set. What is not yet known is the negotiated scope of the design work, whether direct-supervision housing will be priced as part of it, what the renovation will finally cost, and when construction could start or finish.

Advertise your business here

The jail debate lands in a county justice system under fresh scrutiny this month. Lucas County’s courts recently produced the first wrongful-imprisonment declarations in the county’s history, in the cases of five Toledo men whose 1992 convictions were thrown out, and Toledo’s own budget fight has put city staffing, including enforcement jobs, on the table — the same strained local budgets the jail renovation will draw on.

For the people held at the corrections center and the staff who work there, the renovation is the county’s answer to a building officials have criticized for years. The design choices made in the SSOE negotiations — above all the housing model — will decide how the renovated jail operates for decades, not just what it costs to build.

What happens next is the negotiation itself: the commissioners and the two firms must agree on contracts and a scope of work, after which SSOE’s study and cost estimates come back to the board in public session before any construction contract is authorized.