LOGAN — More than 200 people turned out Tuesday evening at Chieftain Elementary School for an Ohio Department of Transportation open house on a planned $153.8 million safety overhaul of U.S. 33 in Hocking County, the Athens Messenger reported.

The project targets the stretch of U.S. 33 from the Fairfield-Hocking county line to Chieftain Drive (state Route 180), a corridor where 256 crashes occurred over a three-to-four-year period with a 36% injury rate, Bryan Newell of the consulting firm Environmental Design Group told the open house, according to the Athens Messenger. “A couple years ago, ODOT was able to secure some money to look at the crashes that were occurring throughout this corridor, and they asked us to help do an analysis of that crash history,” Newell said, in remarks reported by the Athens Messenger.

ODOT’s strategy is to turn this section of 33 into a limited-access highway, separating local traffic from through traffic, the Messenger reported. The plan removes all existing at-grade intersections, installs roundabouts at key intersections, builds about seven miles of new access roads on both sides of the highway so residents and businesses keep driveway access, adds a new interchange at Rockbridge, changes the state Route 180 interchange, relocates Buck Run, and puts in a new bridge at Clear Creek while replacing existing bridges Newell described as “kind of falling apart,” according to the Messenger.

“Some of the things that we can do to make it better… are separating the traffic that is trying to do local things with the traffic that’s just trying to get through here,” Newell said, in remarks reported by the Athens Messenger.

The timeline is long and the money is not yet locked in. Matthew First, an ODOT planning engineer and the project’s manager, told the open house the project has just entered its engineering and detailed design phase, with right-of-way acquisition and utility coordination tentatively set for 2028 and construction in 2030-2031, the Messenger reported. “The project does not have secured construction funding, so our timeline to actually construct the project is still a little bit up in the air. But as we develop the project, our intent is to be ready in 2030 for construction,” First said, in remarks reported by the Athens Messenger.

The estimated budget is $149.8 million for construction and $4 million for right-of-way acquisition, $153.8 million in total, according to the Messenger. ODOT personnel at the open house answered property owners’ questions about land acquisition, and printed material covered the agency’s Relocation Assistance Program, the Messenger reported. ODOT’s project page lists the work under project IDs 115635 and 121463 in District 10.

What happens next is the comment window: ODOT is taking public comments on the project through December 10, 2026, on its project website and through Matthew First at ODOT District 10 in Marietta, the Messenger reported. For the families and businesses along the corridor, those comments are the input that shapes the design phase now underway — years before the first access road is built.