Superior Street in Rossford, OhioSuperior Street in Rossford, Ohio. (Public domain)

ROSSFORD, Ohio — Rossford’s Planning Commission has approved a special use permit and preliminary site plan for a proposed data center on Lime City Road, moving the controversial project one step closer to reality in a region where voters have just spent an election capping exactly this kind of development, according to reporting by 13 Action News (WTVG) summarized by Toledo Buzz.

The planning commission’s approval came just three days after residents packed a November 9, 2026 City Council meeting urging the city to slow down rezoning that could allow the project, according to Toledo Buzz’s summary of the 13 Action News (WTVG) reporting. The November 9 meeting centered on ordinances 2026-68 and 2026-69, which could open the door to heavy industrial uses including a data center.

Residents at that meeting worried a data center would drive up electric bills and strain local infrastructure, according to Toledo Buzz’s summary of the 13 Action News (WTVG) reporting — the same concerns that have driven the ballot fights across northwest Ohio this fall.

The regional contrast is sharp. On November 3, 2026, voters in Oregon, Defiance and Upper Sandusky approved charter amendments restricting large data centers, and Oregon’s measure — supported by nearly 61 percent of voters — effectively blocked a proposed $1 billion data center development near Corduroy and Wynn roads, according to the Toledo Dispatch. Similar measures passed in all 10 Ohio communities voting on large data center bans that day, according to the Toledo Dispatch.

Upper Sandusky’s version shows how decisive some of those votes were: voters there approved a charter amendment prohibiting large data centers — those with a peak electrical load over 25 megawatts — by 1,893 to 568, about 77 percent, after a proposed campus of roughly $900 million divided the city, according to The Fostoria Free Press. Findlay City Council is still working on data center zoning while a 12-month local moratorium runs to April 2027, The Fostoria Free Press reported.

Since the election, the activity has spread: Whitehouse and Waterville are pursuing 10-megawatt caps, and Genoa voters rejected a data center on 430 acres, according to Toledo Buzz’s summary of the 13 Action News (WTVG) reporting. Rossford is now the place where the regional argument runs the other way — a planning body advancing a project while neighboring communities write caps into their charters.

What we know — and what we’re still waiting on: confirmed are the planning commission’s approval of the special use permit and preliminary site plan for the Lime City Road site, and the November 9, 2026 council meeting where residents urged the city to slow the rezoning ordinances down, both from 13 Action News (WTVG) reporting summarized by Toledo Buzz. What is not yet settled is the rezoning itself — ordinances 2026-68 and 2026-69 remain the council’s decision — and with it, whether the permitted site plan can proceed as drawn.

The fight is also moving to the Statehouse: Senate Bill 374, sponsored by Senators Louis Blessing and Kent Smith, would prohibit the state from awarding new data center sales-tax exemptions beginning in October 2027, according to The Fostoria Free Press — a sign that the local votes are now shaping state policy.

What happens next: Rossford City Council’s handling of ordinances 2026-68 and 2026-69 decides whether the Lime City Road rezoning follows the planning commission’s permit — and northwest Ohio’s other towns, fresh off their November 3, 2026 votes, are watching which way a Toledo suburb goes.

By Amy Kowalski

Amy Kowalski is NewsForce247's general assignment reporter for Northwest Ohio, covering the Toledo area and the lake and farm counties around it.

Leave a Reply