Pike County residents are being asked to weigh in on a proposed development agreement for the PORTS-Pike Technology Campus that officials estimate could generate $3.3 billion for the county over 15 years, the Chillicothe Gazette reported.
The framework — involving Pike County, SB Energy and OpenAI — remains nonbinding while the county takes public review and comment, according to a community announcement covered by the Chillicothe Gazette. It would establish a long-term community investment initiative called Pike 2040, funded by payments under the development agreement and administered by a charitable foundation whose board would hold a majority of county-designated representatives alongside company representatives.
Pike 2040 would direct money toward infrastructure, schools, workforce development and other local priorities, the Gazette reported. The proposed agreement would use an alternative to traditional property tax payments, which officials described as giving the county greater predictability in revenue. “Our priority is ensuring that this development supports lasting opportunities for Pike County,” Commissioner Jeff Chattin said in the announcement quoted by the Chillicothe Gazette. “The proposed agreement with the PORTS-Pike Technology Campus will provide our community with accelerated payments and give us revenue certainty.”
Commissioners President Tony Montgomery said county leaders want residents involved before the agreement is completed. “Since the beginning of our work on the PORTS-Pike Technology Campus, the commissioners have focused on a transparent process,” Montgomery said in the announcement quoted by the Chillicothe Gazette. “We have done mailings to every home; held a public open house; encouraged participation at our weekly meetings; created a project website and now seek public input regarding the proposed details in the term sheet.” Montgomery said officials plan to use funding from the agreement for infrastructure improvements in townships and villages and see potential benefits for local schools and students, adding: “The community benefits from this pending agreement are intended to advantage every single citizen of Pike County.”
The county negotiated as one. After SB Energy announced the campus, Pike County’s political subdivisions formed a Council of Governments, and virtually every subdivision joined it to negotiate collectively, according to the announcement. “I am so proud of how our community came together around this project,” Council of Governments President Jennifer Chandler said in the announcement quoted by the Chillicothe Gazette. “Rather than each political subdivision charting its own course, our villages, our townships, and our schools are joining with the County Commissioners to speak with a single voice.”
The campus behind the agreement is one of the largest industrial projects in Ohio history. OpenAI has agreed to secure approximately 8 gigawatts of capacity at the site — the former Portsmouth Gaseous Diffusion Plant near Piketon — working with SB Energy, NVIDIA and the U.S. Department of Energy, according to OpenAI. OpenAI says the project is expected to create 35,000 construction jobs during its six-year buildout through 2032 and 2,500 long-term operating jobs, that SB Energy will pay the full cost of the grid upgrades and transmission lines the campus needs, and that the campus will use closed-loop, air-cooled cooling that recirculates water. OpenAI is investing $40 million in a community grant fund, building on SB Energy’s previously announced $40 million commitment, according to OpenAI.
Under the proposed county agreement, SB Energy would also design, build and fund the public infrastructure improvements needed to serve the campus, including applicable road, water, wastewater and emergency-response improvements, and would collaborate with local labor unions and workforce partners on training and apprenticeships, the Chillicothe Gazette reported.
Residents can comment at the Pike County Board of Commissioners meeting at 9:00 AM on Monday, November 23, 2026, at the Government Center, 230 Waverly Plaza, Suite 100, in Waverly. More information, including a dedicated email address and phone line for questions, is posted at pikecountyohcommissioners.gov/ports. County officials told the Chillicothe Gazette that more detail on the Pike 2040 planning process and foundation will be announced as the initiative moves forward.
Photo: Aesopposea, CC BY-SA 3.0