CHILLICOTHE, Ohio — The company that owns Chillicothe’s former paper mill has brought a dormant collector well back online after a decades-old shaft fractured in the only well it had been running to hold back the Wear-Ever toxic groundwater plume, U.S. Paper Mill said in a November 16, 2026, release reported by the Chillicothe Gazette.
The company first told the Ohio Environmental Protection Agency on November 12, 2026, that a fractured pump was a “potentially urgent situation,” but that statement named no well, the Chillicothe Gazette reported. The November 16 release identified the failure: the shaft fractured in Collector Well 18, and the company shifted pumping to Collector Well 17, which had been dormant. The water table level is being maintained, the company said.
The wells matter because of what sits in the ground east of the mill. Wear-Ever Aluminum operated on Eastern Avenue from 1948 until the late 1990s, and Ohio EPA issued cleanup orders for the site in 1993 and 1999, including for a groundwater plume, according to Ohio EPA’s fact sheet on the site. Howmet Aerospace, the current owner of the Wear-Ever property, is responsible for mitigating the contamination, Ohio EPA says, and the mill’s high-volume wells have helped contain the plume’s flow.
How much margin the system had is now part of the record. Key Environmental Inc., Howmet’s environmental consultant, documented in a 2026 groundwater monitoring report filed with Ohio EPA that Collector Well 17 was not operating during the June 2026 monitoring event and that U.S. Paper Mill had run Well 18 alone since taking ownership of the plant, J News Network reported. The well that broke was, on that record, the only one running.
At a November 16, 2026, public meeting, U.S. Paper Mill utilities superintendent Aaron Anders told the Scioto Post that crews switched to a pump on Well 17 and welded its shaft to get it running again, pumping at least 500 gallons a minute to keep the water table down. The company says employees make rounds every shift to check the wells, and that running the pumps costs at least $1 million a year — work it describes as a voluntary service to Ohio EPA and Howmet since it acquired the closed Pixelle Specialty Solutions plant in 2025.
Ohio EPA’s fact sheet notes the plume is more than a mile and a half from the nearest area that could affect public drinking water sources within five years, and that if the wells stopped, the plume would not move immediately. The agency has directed Howmet to install additional monitoring wells and submit a revised long-term plan for controlling the plume.
What happens next: U.S. Paper Mill continues pumping from Well 17 while Well 18 awaits a replacement shaft the company has said will cost hundreds of thousands of dollars, and Ohio EPA’s monitoring requirements on Howmet remain in force. The episode has given Chillicothe a close look at how much of its protection rests on a single pump.